High School Renovation Project

Section Navigation:

Project Schedule

Below is an overview of the project time line.

 

Task Time Frame Completion Status
Educational Specifications May 29th, 2006 - July 10th, 2006 Completed
Schematic Design July 5th, 2006 - September 25th, 2006 Completed
Design Development September 24th, 2006 - January 22nd, 2007 Completed
Value Engineering October 16th-25th, 2006 Completed
Construction Documents January 22nd, 2007 - May 28th, 2007 Continuing
50% Construction Document Submittal March 12th, 2007 Completed
95% Construction Document Submittal
Constructability Review
May 7th-16th, 2007 Scheduled
School Board Approval to Bid Project May 28th Scheduled
Bidding Period June 18th, 2007 - July 17th, 2007 Scheduled
School Board to Award Contract July 23rd, 2007 Scheduled
Construction August 2007 - December 2008 Scheduled